Rockingham Bridge Project to be complete by September 2020.

Rockingham Bridges – Longest Splice Girder Bridges in New England

The Rockingham Bridges carry Interstate 91 high above the Williams River in Rockingham, Vermont. When the twin replacement bridges were constructed, their precast concrete spliced-girder spans were among the longest of their kind in New England.

I had the opportunity to work on the design of these bridges, making the Rockingham project a particularly interesting example of how splice-girder construction can solve problems that conventional precast girders cannot.

The project also demonstrates how much bridge construction depends on more than structural calculations. Girder size and weight, transportation routes, erection equipment and construction sequencing all influenced the final design. During construction, the team used techniques ranging from rolling highway slowdowns for girder deliveries to installing bearings on the girders before they were erected.

The result was a pair of bridges designed for a 100-year service life—and a useful real-world example of how very long precast concrete girder bridges can be designed, transported and assembled.

The first girders were erected in June of 2018 and the last girders were erected in February 2020.  Once set in place, prestressing strand is pushed into the ducts in the girders and the series of segments is post-tensioned together to form one continuous girder.

While demolition of the northbound bridge involved felling the existing piers like trees, the southbound bridge was a little different.  To expedite construction, the new piers were started prior to demolition of the superstructure.  This meant that the existing piers had to be removed piece-meal.

The piers look extremely slender for being so tall, and they are.  But to get around the contract slenderness limits, two bearings were employed at each girder line at each pier to increase the rotational stiffness, thus modifying the effective length factor of the column which is a measure of the column’s end support conditions.

Much care was taken to achieve a 100 year service life.  Extensive use of stainless steel, dense concrete and up-sized H-piles should allow these bridges to stand for many, many years.

The segments used were some of the largest ever fabricated by J.P. Carrara.  There were weight limitations imposed on the design as well as height limitations, and the final design is a compromise between a great final design and what is possible as far as lifting and delivery. 

Check out these articles, technical papers and presentations which offer more in depth background on the Rockingham Bridge Project.

Design-Build Team Erects Twin Bridges in Vermont by Johanna Knapschaefer – March 17, 2020

Design and Construction of the Rockingham Bridges by Nicholas T. Rodda – September 2017 courtesy of the Western Bridge Engineers’ Seminar. 

IBC 18-30: Replacement of the Rockingham Bridges Using Precast Spliced Girders Technical Paper by Chester Werts and Nicholas T. Rodda – June 12, 2018 courtesy of the International Bridge Conference.  Paper can be ordered at the link above using the paper number, year and author.

Northbound bridge under construction – Summer 2018. Courtesy J.P. Carrara & Sons, Inc.

How Splice Girder Bridges Work

The Rockingham Bridges are a real-world application of precast concrete splice-girder construction. For a closer look at why engineers use splice girders, how the individual girder segments are connected, and how post-tensioning allows them to achieve much longer spans, see:

Spanning Further with Splice Girders

3,012

About the author

Nick Rodda

Nick Rodda is a bridge engineer with nearly two decades of experience designing, inspecting and managing bridges. He writes The Bridge Guy to explore the engineering, history, people and places behind the world’s bridges.

View all posts

4 Comments

Leave a Reply

Your email address will not be published. Required fields are marked *